Corozal Town has completed the implementation of Phase 1 Belize Municipal Development Project, which was officially launched in Corozal on Monday September 24th, 2012. Under the first phase, 1st Street North, Zuzuc Street and Punta Gorda Street were paved. The first phase was completed with $1.2 million being invested in the upgrades.

The second phase of the Corozal projects will commence by the end of November and will see the rehabilitation of 6th Avenue, 1st Street South and a sporting complex will be constructed in the south end of Corozal Town.

Under the Belize Municipal Development Project, the government of Belize is investing $30 million dollars in various municipalities including Belmopan, Benque Viejo Del Carmen, San Ignacio and Santa Elena, Dangriga, Punta Gorda, Corozal and Orange Walk. In Corozal, $2.1 million will be implemented in the various projects.